Library Building Project Update Series (Week of December 21, 2018)
Details
Published
Topping slab is poured; new openings are being created for the former Quaker & Special Collections building that will serve as the doors to the instruction and events space. New water fire line is being installed. Brick delivery on its way.
Read more about the project on the Library Renovation website.
Topping slab is poured; new openings are being created for the former Quaker & Special Collections building that will serve as the doors to the instruction and events space. New water fire line is being installed. Brick delivery on its way.
Magill Library closed at the end of the Fall 2017 semester and will reopen as the Lutnick Library when the construction is completed. Read more about the project on the Library Renovation website.