Library Building Update Series (Week of March 29, 2019)
Details
Published
Ceilings, painting, and brick!
Glass installation almost complete and will be finished tomorrow; ceiling grid on Level 1 installed and next week new ceiling tiles will be installed; Level 2 ceiling grid installation continues. Level 1 room painting completed with primer on Level 2 underway. VCT installation in the Quaker & Special Collections stacks and the Conservation Bindery will be completed this week. Brick installation for the exterior new construction is approximately 30% complete. Shelving installation proceeds.