|
West
Wing (Connecting Hilles to
Sharpless):
- Complete Sharpless renovations:
Summer 2000
- Start of West Wing work: May
2001
- Erect precast structure for West
Wing: August 2001
- Enclose West Wing: January
2002
- West Wing completion:
Summer 2002
|
East Wing
(running along Coursey
Road, South from Sharpless):
- Concrete foundations laid for East
Wing: 5/26/00
- Erect precast structure for East
Wing: Completed 11/3/00
- Steel roof framing:
12/18/00
- Stone veneer started:
10/4/00
- Stone work begins:
12/1/00
- Roofing work starts:
1/10/01
- East Wing enclosed and power: January
2001
- Installation of windows: March
2001
- Installation of casework: April
2001
- Finishing (including paint and
flooring): Spring 2001
- East Wing Completion: July
2001
|